Two separate projects to improve railway stations in Bradford have been delayed.
A £17.3 million project to upgrade Bradford Forster Square Station will not be completed until December 2021 - nine months after the original March 2021 completion date.
The £5.6 million refurbishment of Bradford Interchange is now not likely to be completed until October 2021, 13 months later than the initially proposed September 2020.
According to a report to be presented to members of the West Yorkshire and York Investment Committee, “insufficient expertise” at Bradford Council is behind the Forster Square project delays whilst a “shortage of resource” has halted progress on Bradford Interchange.
Bradford’s Cllr Kamran Hussain Recognised Nationally for Outstanding Community Leadership
Yorkshire’s Winter Wonderland Opens for 20th Anniversary Season at York Designer Outlet
Final Leeds Brown Bin Collections Before Winter ‘Hi-Bin-ation’
Detectives Appeal After Man Seriously Injured in Dewsbury Disorder
Millions of Tenants Protected Under New Awaab’s Law Reforms
Bradford Expands ‘New York’ Style Housing First Approach to Tackle Homelessness
Kensington Palace Marks 150th Birthday of Punjabi Princess and Suffragette Sophia Duleep Singh
SENDIVERSE Festival Unites Bradford Through Creativity and Inclusion
Appeal After Man Seriously Injured in Burnley Collision
Bradford Police Seize 93 Weapons as Knife Crime Falls
Multibillion Economic Vision for Leeds to Create 100,000 Jobs
Building at Bradford Royal Infirmary Renamed in Honour of Renowned Surgeon
Legal Show
Alim OnAir
The Golden Era
Bhangra Nights