Two separate projects to improve railway stations in Bradford have been delayed.
A £17.3 million project to upgrade Bradford Forster Square Station will not be completed until December 2021 - nine months after the original March 2021 completion date.
The £5.6 million refurbishment of Bradford Interchange is now not likely to be completed until October 2021, 13 months later than the initially proposed September 2020.
According to a report to be presented to members of the West Yorkshire and York Investment Committee, “insufficient expertise” at Bradford Council is behind the Forster Square project delays whilst a “shortage of resource” has halted progress on Bradford Interchange.

Fare Dodger Admits Assaulting Police Officer at London Tube Station
Aylesbury Drug Dealer Jailed for Two Years
Leeds in Running to Host 2035 FIFA Women's World Cup Matches
Bradford Hospital Staff Unite to Rescue Stray Cat Family
Richmond Council calls for West London Orbital extension
Seven jailed for helping Iranian nationals enter UK illegally
Leeds man jailed after naming false driver in speeding case
Final four men jailed for child sexual abuse in Bradford case
London SEND School Becomes First in England to Win World's Best School Prize
New and Improved Bus Services Launch Across Blackburn with Darwen
Reopening Keighley Tip Unlikely to Reduce Fly-Tipping, Council Warns
Leeds Economy Strengthens as City Targets 100,000 New Jobs
The Golden Era
Remix Saturdays
Alim OnAir
Legal Show